375 MWp Solar Power Plant,
Andhra Pradesh, India

  • Status

    Commissioned

  • Area of the plant

    1,500 acres

  • Duration

    11 months

  • Homes powered

    55,000

  • Number of people
    who worked on the
    project

    2,100

  • Number of panels

    11,00,000+

  • Safe man-hours

    20,00,000+

  • Key Highlights

    Sterling and Wilson Renewable Energy Limited's largest single-location project in India

    Deployed an advanced robotic module cleaning system for panel maintenance

  • Business Vertical

    Utility Scale