Status
Commissioned
Carbon emissions
saved annually
6,000 tCO2 annually
Turnkey EPC of 3.85 MWp Solar PV + 2.58 MWhr BESS integration into existing DG Network
Extreme remote location of a mine with a completely off-grid solution
Integration with 6 existing DGs currently in operation
Single Axis Tracker and Bifacial Modules used to increase the PV generation in the available land area and footprint
Saving 2 Mn Liter of diesel per annum which is 30% of the client’s diesel consumption per year
Reduction of Carbon 6000 Ton of CO2 per annum
Mobile design of the plant, equipment can be moved to another location after 5 years